Sinohydro Project

Tunnel cross-section: 5.5 × 5m
Gradient: 25°
Length: 550m


Equipment: 8 sets of WDZ180 crawler mucking loaders, 40 sets of KZ4 side dump wagons, 5 sets of TZ4 concrete mixing transport trucks, traction machine, 1.6m and 2m windlass.